Energy from Waste Projects
Detailed Steel Structure Engineering and Fabrication/Erection documentation for Combustion and Boiler, Flue Gas Treatment, Lime Slaker, Pipe racks and Pipe Supports and Bottom Ash Handling system for the following power plant projects:
· 60 MW power plant in Rookery, UK (Covanta Energy Ltd / 2018-2019)
· 60 MW power plant in Rockingham, Perth, Western Australia (Newenergy-Tribe Consortium-HZI / 2019-2020)
· 42 MW power plant in Newhurst, UK (Encyclis / 2020-2021)
· 46 MW power plant in Slough, Greater London, UK (SSE Thermal Ltd-Copenhagen Infrastructure III / 2021-2022)
· 49 MW power plant in Leeds, UK (Enfinium Skelton Grange Ltd / 2022-2023)
- ProjetEnergy from Waste Projects
- Temps d'étude2018-2024
- EmployeurHitachi Zosen Inova
- ProprietaireVarious
- PositionUnited Kingdom & Australia